The project
We supervised this development in Rain. The existing underground parking garage was upgraded so that the two-storey buildings could be constructed above it. Above ground, everything was built in timber with visible wooden ceilings. A busy main road had to be taken into account in terms of building physics.
The construction method
The walls were built using timber frame construction and the floor slabs with cross-laminated timber.
The challenge
We were able to simplify the fire protection requirements considerably with simple measures without compromising safety.
Services of Timbatec
- SIA Phase 31 Vorprojekt
- SIA Phase 32 Bauprojekt
- SIA Phase 41 Ausschreibung und Offertenvergleich
- SIA Phase 51 Ausführungsprojekt
- SIA Phase 52 Ausführung
- SIA Phase 53 Inbetriebnahme
- Fachplanung Bauphysik
- Fachplanung Brandschutz
Holzbau
Implenia Schweiz AG Rümlang
8153 Rümlang
Fotografie
Roland Bernath
Auftraggeber
Edelaar Mosayebi Inderbitzin AG
8003 Zürich